The steam networks of the vacuum factory were implemented and linked to the new factory on 10/8/2016, and the pipes would all smooth schedule 40 lines (6 inches – 3 inches – 2 inches), and a steam battery with a diameter of 1 m, a length of 3 meters, was manufactured. All welds work was Argon and the welds were tested by ( International LOUTS), collection points were carried out and the steam was returned, the Italian Punic steam traps and German traps were supplied and installed, and the thermal insulation works were carried out by specialized engineers, and thanks to the engineers, all works were carried out within 3 months only, and a one-year warranty period was given on all works.